NEW QUESTION 183
Who is responsible for documenting any tailoring of the business case theme?
- A. Corporate management
- B. Project manager
- C. Business project assurance
- D. Executive
Answer: B
Explanation:
Section: Volume B
NEW QUESTION 184
How many management stages should a PRINCE2 project consist of?
- A. Initiation stage and at least one other management stage to cover the remainder of the project
- B. Start up stage, initiation stage and a closing stage
- C. Start up stage, at least one other management stage to cover the remainder of the project and a closing stage
- D. Start up stage, initiation stage and at least one other management stage to cover the remainder of the project
Answer: A
NEW QUESTION 185
Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?
- A. Manage by exception
- B. Manage by stages
- C. Learn from experience
- D. Continued business justification
Answer: A
Explanation:
Section: Volume B
NEW QUESTION 186
Which is part of quality control?
- A. Provide assurance that the project is being conducted properly
- B. Document the customer's quality expectations
- C. Write Product Descriptions
- D. Undertake quality reviews
Answer: D
NEW QUESTION 187
How many roles make up the Project Board?
- A. Two
- B. Four
- C. Three
- D. One
Answer: C
NEW QUESTION 188
Which describes risk probability?
- A. Level of risks which the project can tolerate before escalating to the Project Board
- B. Probable effect on the project delivering its objectives
- C. Timeframe within which the risk may occur
- D. A measure of the likelihood of the risk occurring
Answer: D
NEW QUESTION 189
Which is part of quality control?
- A. Provide assurance that the project is being conducted properly
- B. Document the customer's quality expectations
- C. Write Product Descriptions
- D. Undertake quality reviews
Answer: D
NEW QUESTION 190
How does the 'managing product delivery' process ensure that the team manager's perspective is provided in a work package?
- A. the work packages provided by the project manager are agreed by the team manager
- B. The stage plan covering the work packages is created with input from the team manager
- C. The work packages are defined by the team manager and supported by a team plan
- D. The team plans are checked by project assurance against the work packages
Answer: A
NEW QUESTION 191
Which is a purpose of an End Project Report?
- A. Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed
- B. Identify individuals or groups that need to be told that the project is coming to an end
- C. Review how well the project performed against the Project Initiation Documentation used to authorize it
- D. Ensure that key project information is archived and made secure
Answer: C
NEW QUESTION 192
What is an advantage of applying the 'learn from experience' principle?
- A. It allows the project board to delegate cost tolerances to the project manager
- B. It allows the project team to fully understand their roles and responsibilities
- C. It allows the project manager to delegate time tolerances to the team managers
- D. It allows the project team to identify improvements to be made during the project
Answer: D
NEW QUESTION 193
Which is a minimum requirement for applying the organization theme?
- A. The project team must change at each end stage of the project life cycle
- B. During a procurement the senior supplier must be appointed from the customer organization
- C. The project's approach to engaging with its stakeholders must be defined
- D. Roles must be combined to reduce the number of individuals needed on the project
Answer: C
NEW QUESTION 194
Which activity takes place within the Managing a Stage Boundary process?
- A. Produce an Exception Plan
- B. Authorize a Stage Plan for the next stage
- C. Take corrective action within the limits of a stage's tolerance
- D. Produce Highlight Reports
Answer: A
Explanation:
Section: Volume B
NEW QUESTION 195
Which PRINCE2 principle helps to address a concern that the project team may NOT have worked on a similar project?
- A. Defined roles and responsibilities
- B. Manage by exception
- C. Focus on products
- D. Learn from experience
Answer: D
Explanation:
Explanation
Reference https://www.prince2primer.com/academy/uncategorized/
NEW QUESTION 196
Which plan provides the Business Case with costs during the Initiating a Project process?
- A. Team Plan
- B. Stage Plan
- C. Project Plan
- D. Initiation Stage Plan
Answer: C
Explanation:
Section: Volume A
Explanation
NEW QUESTION 197
Which risk response is applied on a pain/gain basis?
- A. Enhance
- B. Exploit
- C. Accept
- D. Share
Answer: D
Explanation:
Section: Volume B
Explanation/Reference: https://www.prince2primer.com/prince2-2017-risk-responses-and-planning/
NEW QUESTION 198
Which is a responsibility of the project board?
- A. To ensure production of the project's outputs
- B. To implement the change control approach
- C. To manage the team managers and project support
- D. To ensure effective communication with external stakeholders
Answer: D
Explanation:
Reference: http://prince2.wiki/Organization#Project_Board
NEW QUESTION 199
Which statement about the quality review technique is FALSE?
- A. It enables a check to be made on a product's fitness for purpose
- B. It is used to gain wider acceptance of a product by involving key interested parties
- C. It supports the management of future changes by providing a baseline for a product
- D. It defines the quality responsibilities of the project team
Answer: D
Explanation:
Section: Volume B
NEW QUESTION 200
Identify the missing words in the following sentence.
PRINCE2 requires that the business case is formally verified by [?] at stage boundaries.
- A. the project manager
- B. corporate, programme management or the customer
- C. the project board
- D. the change authority
Answer: C
NEW QUESTION 201
What must be produced to meet the minimum requirements for applying the change theme?
- A. Details of the status of all products being produced
- B. Documentation on the version of each product
- C. Documentation on the corrective action for an issue
- D. Details of the decisions taken on all issues
Answer: D
Explanation:
Explanation/Reference:
Reference http://prince2.wiki/Themes#Change_Theme
NEW QUESTION 202
Which is a recommended quality review team role?
- A. Administrator
- B. Assurance
- C. Project Support
- D. Project Manager
Answer: A
NEW QUESTION 203
......