Get Special Discount Offer of PMI-RMP Certification Exam Sample Questions and Answers [Q148-Q170]

Share

Get Special Discount Offer of PMI-RMP Certification Exam Sample Questions and Answers

New PMI-RMP Dumps For Preparing Project Management Professional Certified PMI Exam Well

NEW QUESTION # 148
The risk manager for an IT project developing a software application has a major stakeholder concerned that the project will not conclude within the available funding. The risk manager found delays in the iterations and increments in the project's budget, potentially increasing the duration by two weeks.
What tools should the risk manager use to properly decide the risk of not finishing the project within the budget?

  • A. Team performance reports and analysis tools
  • B. Schedule management tools (i.e., Gantt Charts)
  • C. Estimation and probability analysis tools (i.e. Monte Carlo simulations)
  • D. Stakeholder management and communication tools

Answer: C


NEW QUESTION # 149
After completing the risk register, many team members feel there is a lack of time prioritization for one of the identified risks What are the team members referring to?

  • A. Risk time impact
  • B. Risk urgency
  • C. Risk trigger
  • D. Risk escalation

Answer: B

Explanation:
Risk urgency refers to the timeframe within which a risk might occur and necessitates prioritization based on how soon a response is required. When team members express concerns about a lack of time prioritization for an identified risk, they are highlighting the need to assess and address the risk's urgency. Evaluating risk urgency involves determining the proximity of the risk event and ensuring that timely actions are planned to mitigate or respond to the risk appropriately. Incorporating urgency assessments into the risk management process helps in allocating resources and attention to risks that require immediate action, thereby enhancing the project's resilience against potential threats.
PMI Risk Management Study Guide References:
The PMI-RMP Exam Preparation Study Guide discusses the concept of risk urgency, noting that
"understanding the timing of potential risk events is crucial for effective prioritization and response planning."


NEW QUESTION # 150
A risk manager faces resistance as they try to implement the project's risk strategy. Some members of the project team believe it is a waste of time and money, What should the risk manager do?

  • A. Meet with team members to address their concerns.
  • B. Continue to implement the risk strategy
  • C. Reduce the number of risk management activities.
  • D. Raise the concerns with the project sponsor,

Answer: A

Explanation:
When facing resistance from team members, the risk manager should engage in open communication to address their concerns and clarify the importance of risk management in the project.
According to the PMBOK Guide, 6th edition, Chapter 11: Project Risk Management1, the risk manager should handle this situation by meeting with team members to address their concerns. This is because:
Resistance to risk management is a common challenge that can hinder the effectiveness and efficiency of the risk management process. Resistance can stem from various factors, such as lack of awareness, understanding, commitment, trust, or support for risk management; fear of negative consequences or blame; competing priorities or interests; or cultural differences or biases.
Meeting with team members to address their concerns is a proactive and constructive way to overcome resistance and foster a positive risk culture within the project. By meeting with team members, the risk manager can:
Communicate the value and benefits of risk management for the project and the organization, such as improving decision-making, enhancing performance, increasing stakeholder satisfaction, and reducing uncertainty and variability.
Educate and train team members on the risk management principles, processes, tools, and techniques, and how they can be applied to the project context and objectives.
Involve and empower team members in the risk management activities, such as identifying, analyzing, prioritizing, responding, and monitoring risks, and solicit their feedback and suggestions for improvement.
Recognize and reward team members for their contributions and achievements in risk management, and celebrate the successful outcomes and opportunities realized by the project.
The other options are not effective in handling this situation because:
Continuing to implement the risk strategy without addressing the resistance can lead to further conflict, resentment, and distrust among the team members, and undermine the quality and credibility of the risk management process and outputs.
Reducing the number of risk management activities can compromise the project's ability to identify and respond to the risks that may affect its scope, schedule, cost, quality, or other objectives, and expose the project to unnecessary threats or missed opportunities.
Raising the concerns with the project sponsor can escalate the issue and create a negative impression of the team members, and may not resolve the underlying causes of the resistance or improve the team's engagement and commitment to risk management.
PMBOK Guide, 6th edition, Chapter 11: Project Risk Management1
Risk Management Professional (PMI-RMP) Exam Cert Guide2


NEW QUESTION # 151
A project manager is developing the risk register and works with the team to analyze risks and determine their probability and impact. There is valuable historical data available that may be used to simulate the overall risk outcome.
Which type of analysis should the project manager use in this instance?

  • A. Cause and effect
  • B. Quantitative analysis
  • C. Specialized meeting
  • D. Check list analysis

Answer: B

Explanation:
Explanation
In this instance, the project manager should use quantitative analysis to simulate the overall risk outcome.
Quantitative analysis techniques, such as Monte Carlo simulation or decision tree analysis, can be used to model the combined effect of individual risks on project objectives. By leveraging historical data, the project manager can generate more accurate and reliable risk assessments, which can help inform risk response strategies and improve project decision-making.


NEW QUESTION # 152
Your project team has identified a project risk that must be responded to. The risk has been recorded in the risk register and the project team has been discussing potential risk responses for the risk event. The event is not likely to happen for several months but the probability of the event is high. Which one of the following is a valid response to the identified risk event?

  • A. Technical performance measurement
  • B. Earned value management
  • C. Risk audit
  • D. Corrective action

Answer: D


NEW QUESTION # 153
You are the project manager of the GGG project. You have completed the risk identification process for the initial phases of your project. As you begin to document the risk events in the risk register what additional information can you associate with the identified risk events?

  • A. Risk cost
  • B. Risk potential responses
  • C. Risk schedule
  • D. Risk owner

Answer: B


NEW QUESTION # 154
You are the project manager of the GGH Project in your company. Your company is structured as a functional organization and you report to the functional manager that you are ready to move onto the quantitative risk analysis process. What things will you need as inputs for the quantitative risk analysis of the project in this scenario?

  • A. You will need the risk register, risk management plan, cost management plan, schedule management plan, and any relevant organizational process assets.
  • B. You will need the risk register, risk management plan, outputs of qualitative risk analysis, and any relevant organizational process assets.
  • C. Quantitative risk analysis does not happen through the project manager in a functional structure.
  • D. You will need the risk register, risk management plan, permission from the functional manager, and any relevant organizational process assets.

Answer: A


NEW QUESTION # 155
The project risk manager is in the process of identifying risks. The project sponsor has communicated that there is an influential stakeholder who has a senior management position. The other stakeholders do not feel comfortable speaking in front of this stakeholder.
What should the project risk manager do next to identify risks?

  • A. Review the risk breakdown structure to ensure project scope is covered.
  • B. Consider the Delphi technique to gather all stakeholder opinions.
  • C. Use expert judgment to remove ego or emotional conflict.
  • D. Use the brainstorming technique to remove personal bias.

Answer: B

Explanation:
Explanation
The Delphi technique allows the project risk manager to gather opinions from all stakeholders anonymously.
This method would enable stakeholders to express their concerns without feeling uncomfortable in front of the influential stakeholder.
The Delphi technique is a tool used to make quick decisions with consensus. This technique consists of sending several sets of anonymous questions to each expert. This is followed by a group discussion after every round. The Delphi technique can help the project risk manager to identify risks by soliciting the opinions of all stakeholders without revealing their identities. This way, the stakeholders can express their views freely and honestly, without being influenced or intimidated by the influential stakeholder. The Delphi technique can also reduce personal bias, ego, or emotional conflict among the participants. The project risk manager can use the results of the Delphi technique to create a list of potential risks and their causes, effects, and probabilities.
References: 3, 2, 5


NEW QUESTION # 156
A project manager is educating the project team on risk management regarding the role of threats and opportunities. The team decides to log the opportunities in the current project's risk register to try to maximize their chances of occurrence.
What should the project team do next?

  • A. Update the project management plan to ensure the results of the opportunities are captured.
  • B. Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis.
  • C. Log the threats in the risk register to try to maximize the probability of occurrence.
  • D. Log the threats in the risk register to try to minimize the probability of occurrence.

Answer: A

Explanation:
According to the PMI Risk Management Professional (PMI-RMP) Reference Materials, the project management plan is the document that describes how the project will be executed, monitored, and controlled. It integrates and consolidates all the subsidiary plans and baselines from the project management processes1. The project management plan should be updated whenever there are changes in the project scope, schedule, cost, quality, resources, communications, risks, procurements, or stakeholder engagement2. In this case, the project team has decided to log the opportunities in the current project's risk register, which is a component of the project management plan. Opportunities are positive risks that may have a beneficial effect on the project objectives, such as cost savings, schedule acceleration, or quality improvement3. Therefore, the project team should update the project management plan to ensure the results of the opportunities are captured and reflected in the relevant subsidiary plans and baselines. For example, if an opportunity leads to a cost saving, the project team should update the cost management plan and the cost baseline accordingly.


NEW QUESTION # 157
You work as a project manager for BlueWell Inc. You are preparing for the risk identification process. You will need to involve several of the project's key stakeholders to help you identify and communicate the identified risk events. You will also need several documents to help you and the stakeholders identify the risk events.
Which one of the following is NOT a document that will help you identify and communicate risks within the project?

  • A. Activity duration estimates
  • B. Stakeholder register
  • C. Activity cost estimates
  • D. Risk register

Answer: D


NEW QUESTION # 158
You are the project manager for your organization. You are working with your project team to complete the qualitative risk analysis process. The first tool and technique you are using requires that you assess the probability and what other characteristic of each identified risk in the project?

  • A. Risk category
  • B. Impact
  • C. Cost
  • D. Risk owner

Answer: B

Explanation:
Explanation/Reference:


NEW QUESTION # 159
The senior risk manager hears that critical deliverables are delayed, because a key subject matter expert (SME) does not have enough time to allocate to the tasks. Which area should be reviewed, as an opportunity for the risk manager to coach the project manager responsible for the project?

  • A. Risk identification process and participation
  • B. Detailed review of the project schedule before approval
  • C. Risk management plan and planned risks responses
  • D. Scope reduction to reduce SME reliance

Answer: D

Explanation:
Explanation/Reference:


NEW QUESTION # 160
A product roadmap should contain which of these primary components?

  • A. Project release timeframes, detailed design plan
  • B. Detailed design plan, business objectives, timeframes
  • C. Product vision, business objectives, timeframes
  • D. Project management plan, communications management plan, stakeholder engagement plan

Answer: C

Explanation:
Comprehensive and Detailed In-Depth Explanation:
A product roadmap is a strategic document that outlines the vision, direction, and progress of a product over time. It serves as a communication tool, aligning stakeholders on the product's goals and the plan to achieve them.
Option D: Product vision, business objectives, timeframes.
This option encapsulates the essential elements of a product roadmap:
Product Vision: Defines the long-term mission and purpose of the product, providing a clear direction and inspiration.
Business Objectives: Specific, measurable goals that the product aims to achieve, aligning with the organization's strategic aims.
Timeframes: Indicative timelines for achieving milestones, helping to set expectations and facilitate planning.
The PMI-RMP Exam Prep Study Guide highlights that "a well-structured product roadmap includes the product vision, aligned business objectives, and projected timeframes to guide development and stakeholder communication" (Fremouw, 2021, p. 89).
Option A: Detailed design plan, business objectives, timeframes.
While business objectives and timeframes are integral to a product roadmap, a detailed design plan is typically too granular for this high-level document. The roadmap focuses on overarching goals and timelines rather than specific design details.
Option B: Project management plan, communications management plan, stakeholder engagement plan.
These components are elements of project management planning but do not constitute a product roadmap.
They pertain to the processes and methodologies of managing a project rather than outlining the strategic direction of a product.
Option C: Project release timeframes, detailed design plan.
Project release timeframes are relevant to a product roadmap; however, combining them solely with a detailed design plan omits the critical aspects of product vision and business objectives, which are necessary to provide context and purpose.
In summary, a comprehensive product roadmap should primarily include the product vision, business objectives, and timeframes (Option D), offering a strategic overview that guides the product's development and aligns stakeholders with its intended direction.
References:
Fremouw, B. (2021). PMI-RMP Exam Prep Study Guide. RMC Publications.


NEW QUESTION # 161
You are the project manager of a large construction project. This project will last for 18 months and will cost $750,000 to complete. You are working with your project team, experts, and stakeholders to identify risks within the project before the project work begins. Management wants to know why you have scheduled so many risk identification meetings throughout the project rather than just initially during the project planning. What is the best reason for the duplicate risk identification sessions?

  • A. The iterative meetings allow all stakeholders to participate in the risk identification processes throughout the project phases.
  • B. The iterative meetings allow the project manager and the risk identification participants to identify newly discovered risk events throughout the project.
  • C. The iterative meetings allow the project manager to discuss the risk events which have passed the project and which did not happen.
  • D. The iterative meetings allow the project manager to communicate pending risks events during project execution.

Answer: B


NEW QUESTION # 162
You are the project manager of the GHQ project for your company. You are working with your project team to prepare for the qualitative risk analysis process. Mary, a project team member, does not understand why you need to complete qualitative risks analysis. You explain to Mary that qualitative risks analysis helps you determine which risks needs additional analysis. There are also some other benefits that qualitative risks analysis can do for the project. Which one of the following is NOT an accomplishment of the qualitative risk analysis process?

  • A. Prioritization of identified risk events based on probability and impact
  • B. Corresponding impact on project objectives
  • C. Time frame for a risk response
  • D. Cost of the risk impact if the risk event occurs

Answer: D


NEW QUESTION # 163
Elizabeth is a project manager for her organization and she finds risk management to be very difficult for her to manage. She asks you, a lead project manager, at what stage in the project will risk management become easier. What answer best resolves the difficulty of risk management practices and the effort required?

  • A. Risk management is an iterative process and never becomes easier.
  • B. Risk management only becomes easier when the project moves into
    project execution.
  • C. Risk management only becomes easier when the project is closed.
  • D. Risk management only becomes easier the more often it is practiced.

Answer: D


NEW QUESTION # 164
When selecting strategies as an activity of Plan Risk Response, what is the overall goal?

  • A. Select the strategies with the greatest benefit to stakeholders.
  • B. Select the strategies with the least overall impact to resources.
  • C. Select the strategies with the least financial impact.
  • D. Select the strategies with the greatest overall positive influence.

Answer: D

Explanation:
The overall goal of selecting strategies during the Plan Risk Response activity is to choose those strategies that have the greatest overall positive influence on the project, considering factors such as cost, schedule, and resources.
According to the PMI Risk Management Professional (PMI-RMP)® Examination Content Outline1, one of the tasks in the domain of Risk Response is to select risk response strategies based on the risk appetite and tolerance of the organization and stakeholders1. The overall goal of selecting risk response strategies is to select the strategies with the greatest overall positive influence on the project objectives, such as scope, schedule, cost, quality, etc. The risk response strategies should aim to enhance the opportunities and reduce the threats to the project, while considering the cost-benefit analysis, the feasibility, and the alignment with the project goals and stakeholder expectations2. The risk response strategies should not be selected based on the least overall impact to resources, because that may not be the mosteffective or efficient way to address the risks, and itmay ignore the potential benefits of some strategies that may require more resources but also deliver more value3. The risk response strategies should not be selected based on the least financial impact, because that may not be the most relevant or comprehensive criterion to evaluate the risks, and it may overlook other aspects of the project, such as quality, customer satisfaction, reputation, etc. that may also be affected by the risks4. The risk response strategies should not be selected based on the greatest benefit to stakeholders, because that may not be the most realistic or achievable goal, and it may create conflicts or trade-offs among different stakeholder groups that may have different or competing interests, needs, and expectations5. References: 1: PMI Risk Management Professional (PMI-RMP)® Examination Content Outline, page 102: A Guide to the Project Management Body of Knowledge (PMBOK® Guide) - Sixth Edition, page 4403: A Guide to the Project Management Body of Knowledge (PMBOK® Guide) - Sixth Edition, page 4414: AGuide to the Project Management Body of Knowledge (PMBOK® Guide) - Sixth Edition, page 4425: A Guide to the Project Management Body of Knowledge (PMBOK® Guide) - Sixth Edition, page 518.


NEW QUESTION # 165
You work as a project manager for BlueWell Inc. You are currently working with the project stakeholders to identify risks in your project. You understand that the qualitative risk assessment and analysis can reflect the attitude of the project team and other stakeholders to risk. Effective assessment of risk requires management of the risk attitudes of the participants. What should you, the project manager, do with assessment of identified risks in consideration of the attitude and bias of the participants towards the project risk?

  • A. Evaluate the bias towards the risk events and correct the assessment accordingly
  • B. Evaluate the bias through SWOT for true analysis of the risk events
  • C. Evaluate and document the bias towards the risk events
  • D. Document the bias for the risk events and communicate the bias with management

Answer: A


NEW QUESTION # 166
A new risk manager has been hired on a project and meets with the project director. The project director supplies the project's risk register and asks the risk manager for an analysis of its effectiveness.
What two actions should the risk manager do next? (Choose two.)

  • A. Check to ensure that risk origin, triggering event, and ownership is identified.
  • B. Check to ensure that the risks are gathered using Delphi technique.
  • C. Check to ensure the risk meeting agenda and supporting documents are distributed.
  • D. Check for risk classification and that probability and impact are identified.
  • E. Check to ensure that the risk is supported by a Monte Carlo simulation.

Answer: A,D

Explanation:
Explanation
The risk manager should first check the risk register for proper risk classification, probability, and impact (C), as these are essential components of an effective risk management process. Next, the risk manager should ensure that the risk origin, triggering events, and ownership are identified (D), as this information helps in assigning responsibilities and taking appropriate actions for each risk. References to these steps can be found in the Project Management Institute's (PMI) A Guide to the Project Management Body of Knowledge (PMBOK Guide), Sixth Edition.
The risk manager should check for risk classification and that probability and impact are identified, as these are essential elements of a risk register. Risk classification helps to group risks into categories based on their sources, types, or impacts, which can facilitate risk analysis and response planning. Probability and impact are the two dimensions of risk assessment, which help to measure the likelihood and severity of a risk event, and to prioritize risks based on their significance. The risk manager should also check to ensure that risk origin, triggering event, and ownership is identified, as these are also important components of a risk register. Risk origin refers to the root cause or source of a risk, which can help to understand the nature and characteristics of a risk, and to devise effective risk responses. Triggering event is a specific occurrence or condition that indicates that a risk event has occurred or is about to occur, which can help to monitor and control risks.
Ownership is the assignment of a risk to a person or a group who is responsible for managing the risk, which can help to ensure accountability and communication. The risk manager should not check to ensure that the risk is supported by a Monte Carlo simulation, as this is not a mandatory or universal requirement for a risk register. Monte Carlo simulation is a quantitative risk analysis technique that uses computer-generated random scenarios to model the possible outcomes of a project, based on the probability distributions of the input variables. While this technique can provide useful information about the overall project risk exposure and the probability of achieving project objectives, it is not a necessary or sufficient condition for an effective risk register. The risk manager should not check to ensure that the risks are gathered using Delphi technique, as this is also not a compulsory or exclusive requirement for a risk register. Delphi technique is a qualitative risk identification technique that uses a panel of experts to anonymously provide their opinions on potential risks, which are then aggregated and refined through a series of rounds until a consensus is reached. While this technique can help to elicit expert judgment and reduce bias, it is not the only or the best way to identify risks.
The risk manager should not check to ensure the risk meeting agenda and supporting documents are distributed, as this is not a relevant or appropriate action for analyzing the effectiveness of a risk register. The risk meeting agenda and supporting documents are part of the risk management plan, which describes how the project team will conduct risk management activities, such as identifying, analyzing, responding, and monitoring risks. The risk meeting agenda and supporting documents are useful for planning and conducting risk meetings, but they are not part of the risk register, which is the output of the risk identification process and the input for the risk analysis and response processes. References: PMI. (2017). A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Sixth Edition. Chapter 11: Project Risk Management, pp. 395-454. 5


NEW QUESTION # 167
Some project risks are applicable for the project's lifecycle while others risks are only applicable to specific project activities. When should project risks be closed?

  • A. When the forecast activity date has been met or exceeded
  • B. When the stakeholders agree a risk is no longer applicable
  • C. When the risk has been realized and can no longer happen again
  • D. When iterative data analysis determines the risk is not applicable

Answer: B

Explanation:
Project risks should be closed when the stakeholders agree a risk is no longer applicable. This ensures that risks are actively managed and only relevant risks are considered throughout the project lifecycle.
According to the PMI Risk Management Professional (PMI-RMP) Reference Materials, project risks are uncertain events or conditions that may have a positive or negative effect on one or more project objectives1.
Project risks can be closed when they are no longer applicable to the project or its activities. The process of closing project risks involves verifying that the risk responses have been completed, documenting the outcomes, and evaluating the effectiveness of the risk management process2. The decision to close a project risk should be made by the stakeholders who are responsible for or affected by the risk, as they are the ones who can determine whether the risk is still relevant or not. Therefore, the correct answer is B. When the stakeholders agree a risk is no longer applicable.
References: 1: PMI, A Guide to the Project Management Body of Knowledge (PMBOK® Guide), Sixth Edition, 2017, p. 397 2: PMI, Practice Standard for Project Risk Management, 2009, p. 111


NEW QUESTION # 168
You are the project manager of the NHQ project for your company. Management has told you that you must implement an agreed upon contingency response if the Cost Performance Index in your project is less than 0.90. Consider that your project has a budget at completion of $250,000 and is 60 percent complete. You are scheduled to be however, 75 percent complete, and you have spent $165,000 to date. What is the Cost Performance Index for this project to determine if the contingency response should happen?

  • A. 0.80
  • B. 0.91
  • C. 0.88
  • D. -$37,500

Answer: B


NEW QUESTION # 169
You work as the project manager for Bluewell Inc. You are working on NGQQ Projectyou're your company. You have completed the risk analysis processes for the risk events. You and the project team have created risk responses for most of the identified project risks. Which of the following risk response planning techniques will you use to shift the impact of a threat to a third party, together with the responses?

  • A. Risk avoidance
  • B. Risk transference
  • C. Risk acceptance
  • D. Risk mitigation

Answer: B


NEW QUESTION # 170
......

Updated PMI-RMP Dumps Questions Are Available For Passing PMI Exam: https://www.examdumpsvce.com/PMI-RMP-valid-exam-dumps.html

Free UPDATED PMI PMI-RMP Certification Exam Dumps is Online: https://drive.google.com/open?id=1tRX5ty-qqXOkCg0s3Zb2AsW3MMuR9XeC