NEW QUESTION 43
Which risk response encourages collaboration on risk management activities?

  • A. Reduce
  • B. Avoid
  • C. Prepare contingent plans
  • D. Share

Answer: D

 

NEW QUESTION 44
Why does a programme require a continual process of realignment?

  • A. The programme plan describes the activities required to implement its projects
  • B. Programmes need to be able to respond to changes in corporate strategy
  • C. An organization's projects should belong to a single programme
  • D. Programmes deal with outcomes whereas projects deal with outputs

Answer: A

 

NEW QUESTION 45
Which statement is NOT valid for the path to benefit realization and corporate objectives?

  • A. Outcomes contribute to capabilities which trigger organizational change
  • B. Outcomes are enabled by capabilities and followed by realization of benefits
  • C. Outcomes are enabled by organizational change and can cause side effects
  • D. Outcomes lead to realization of benefits which contribute to corporate objectives

Answer: C

 

NEW QUESTION 46
What should the programme manager provide for projects before they start?

  • A. A project plan
  • B. A project risk register
  • C. A project tolerance level
  • D. A detailed project specification

Answer: A

 

NEW QUESTION 47
Which describes an impact of a risk?

  • A. Possibility that something will go wrong
  • B. The amount of risk that will be tolerated
  • C. An event that might increase a programme's outcome
  • D. Effect on the programme if something goes wrong

Answer: D

 

NEW QUESTION 48
When applying the vision governance theme, which is an area of focus for the senior responsible owner?

  • A. To assess the impact of the vision statement on business operation
  • B. To ensure that the organization is capable of achieving the transformation described
  • C. To deliver the operational changes needed to achieve the desired end state
  • D. To ensure that the vision statement supports the programme communications plan

Answer: C

 

NEW QUESTION 49
What role authorizes improvements to the wording of the Vision Statement in order to provide greater clarity for stakeholders?

  • A. Senior Responsible Owner
  • B. Programme Assurance
  • C. Programme Manager
  • D. Business Change Manager

Answer: A

 

NEW QUESTION 50
What type of programme may also be referred to as a 'must do' programme?

  • A. Emergent
  • B. Compliance
  • C. Vision-led
  • D. Portfolio

Answer: B

 

NEW QUESTION 51
Which is a trigger for a compliance programme?

  • A. The organization chooses to take a new innovative approach to product development
  • B. The organization has to change to meet requirements of new legislation
  • C. A number of stand-alone projects would benefit from better coordination
  • D. The corporate board has created a vision for change

Answer: B

 

NEW QUESTION 52
Which is a transformational flow process?

  • A. Issue Management Cycle
  • B. Managing the Tranches
  • C. Planning and Control
  • D. Monitoring and Control Strategy

Answer: B

 

NEW QUESTION 53
Which is an assurance management technique?

  • A. Change control
  • B. Issue management
  • C. Gated reviews
  • D. Quality management

Answer: C

 

NEW QUESTION 54
Which information about a project should be included in the Projects Dossier?

  • A. Names of the project team members
  • B. How the outputs will be implemented into the business
  • C. Project brief for the project
  • D. Contribution the project will make to the programme's benefits

Answer: B

 

NEW QUESTION 55
Which is a feature of an effective programme organization?

  • A. A quality assured configuration management system
  • B. Clear accountability for each management role
  • C. A business case agreed by the stakeholders
  • D. Monitored and controlled programme changes

Answer: D

 

NEW QUESTION 56
Which document is updated throughout the programme when new information on benefits and risks becomes available?

  • A. Benefits Management Strategy
  • B. Information Management Plan
  • C. Programme Brief
  • D. Business Case

Answer: B

 

NEW QUESTION 57
What programme role is MOST likely to also have a role within a project board to represent the interests of the business?

  • A. Programme Board
  • B. Programme Manager
  • C. Business Change Manager
  • D. Programme Office

Answer: A

 

NEW QUESTION 58
What role is responsible for tracking the progress of risk responses?

  • A. Risk Manager
  • B. Risk owner
  • C. Design Authority
  • D. Risk actionee

Answer: B

 

NEW QUESTION 59
Which of the following statements about the core elements of successful communications is true?
1. Stakeholder analysis is required
2. Audit trail is established

  • A. Only 2 is true
  • B. Both 1 and 2 are true
  • C. Neither 1 or 2 is true
  • D. Only 1 is true

Answer: D

 

NEW QUESTION 60
Which activity requires the programme office to be independent of the initiatives?

  • A. Project guidance
  • B. Administrative duties
  • C. Control of standards
  • D. Project support

Answer: A

 

NEW QUESTION 61
......