NEW QUESTION 22
In a Lean Software Development environment, the Project Leader strives to eliminate:

  • A. Defects and features with low value stream values.
  • B. Delays and building what is not needed.
  • C. Work in Process (WIP) and bugs.
  • D. Poor requirements and changing scope.

Answer: A

Explanation:
Explanation/Reference:

 

NEW QUESTION 23
A scrum team has conducted regular retrospectives to discuss immediate concerns and the implementation of improvement actions. Despite this, after a few iterations, the same concerns resurface.
What should the team have done to improve retrospective outcomes?

  • A. Invited subject matter experts (SMEs)
  • B. Conducted problem detection to determine root causes
  • C. Kept track of all current issues in a log, and then reviewed their progress at the end of every iteration
  • D. Measured and reported the outcome of improvement actions to the team

Answer: B

 

NEW QUESTION 24
When estimating initial velocity, the team should most likely:

  • A. Discuss with the customer their expectation for the velocity of producing the product.
  • B. Discuss among the team their expectations of how many story points they can address.
  • C. Use velocity of past iterations or make a calculated guess.
  • D. Use a Kanban workflow to identify steps and calculate velocity.

Answer: C

Explanation:
Explanation/Reference:

 

NEW QUESTION 25
What should a team consider when calculating the effort needed to complete a product backlog?

  • A. Assigning extra points to each task to allow time for changes
  • B. The increase in velocity and cost
  • C. A buffer in the sprint to mitigate unexpected risks
  • D. Stories describing infrastructure tasks and analysis tasks

Answer: D

 

NEW QUESTION 26
During a review session, a customer representative is concerned that a story fails to satisfy the scope of work. However, the product owner declares that the scope of work is complete.
What should be done with this story?

  • A. Mark it as complete, since the team completed the scope of work
  • B. Mark it as incomplete and prioritize it for the next sprint
  • C. Mark it as complete, since the product owner has the final say
  • D. Discard it and create a new story for the remaining scope of work

Answer: B

 

NEW QUESTION 27
Why should a project team reduce the work in process?

  • A. It indicates poor project Quality
  • B. It represents unrealized value
  • C. It represents team members" utilization.
  • D. It shows that the project is behind schedule

Answer: B

 

NEW QUESTION 28
The primary purpose of a Sprint Review is for the team to:

  • A. Prioritize and estimate stories planned for the next sprint.
  • B. Demonstrate what was accomplished during the sprint.
  • C. Individually provide status updates on user stories in progress.
  • D. Discuss what went well, whatdidn't, and ways to improve.

Answer: B

Explanation:
Explanation/Reference:
Explanation:

 

NEW QUESTION 29
Pareto Analysis is the exercise of determining what 40% of functionality can be delivered with
60% of the effort.

  • A. False
  • B. True

Answer: A

 

NEW QUESTION 30
During which activity is the sequence of numbers 0, 1, 2, 3, 5, 8, 13 often used?

  • A. Estimating points of a story
  • B. Estimating development hours
  • C. Denoting development sequence
  • D. Indicating priority of a story

Answer: A

 

NEW QUESTION 31
Who can change the Sprint Backlog during a Sprint?

  • A. The Development Team
  • B. The Scrum Master
  • C. Senior Executives
  • D. The Product Owner

Answer: A

 

NEW QUESTION 32
The velocity chart, storyboard, burndown chart, and impediment list are often communicated using:

  • A. Project data packages.
  • B. Information radiators.
  • C. Portfolio presentations.
  • D. Status reports.

Answer: B

 

NEW QUESTION 33
The person responsible for the Scrum process, making sure it is used correctly and maximizing its benefit:

  • A. Product Owner
  • B. Scrum Manager
  • C. Coach
  • D. Scrum Master

Answer: D

Explanation:
Explanation

 

NEW QUESTION 34
What is the Agile Open Space concept?

  • A. The choice to collocate all team members for the beginning of a project.
  • B. It is a meeting designed to allow Agile practitioners to meet in self-organizing groups where they can share their latest ideas and challenges.
  • C. When cubicles walls are removed for an Agile team.
  • D. It is a core principle of ADSM

Answer: B

 

NEW QUESTION 35
An Agile team expects a velocity of 8. During sprint planning, the stories were estimatedand prioritized in the following order:
Story A_4Story Points
Story B_2Story Points
Story C_3 Story Points
Story D_2Story Points
Which stories should the team include in Sprint 1, without splitting the stories?

  • A. Stories A, C, and D
  • B. Stories A, B, and D
  • C. Stories A, B, and C
  • D. Stories B, C, and D

Answer: B

 

NEW QUESTION 36
An iteration takes place in a time frame with specific start and end dates, called a time-box. Which of the following is NOT an advantage of time-boxing?

  • A. Establishes a WIP limit
  • B. Demonstrates progress
  • C. Helps control technical debt
  • D. Forces prioritization

Answer: C

 

NEW QUESTION 37
Which 2 are goals of Lean Software Development? (Choose two.)

  • A. Minimize waste
  • B. Continuous integration
  • C. Simple Design
  • D. Ensure value

Answer: A,D

 

NEW QUESTION 38
For a critical project, a new team has been formed from various departments. The project manager should start team building by:

  • A. Assembling the team and discussing roles and responsibilities of each member on the team.
  • B. Assembling the team and asking the members to achieve a milestone in a small iteration.
  • C. Taking the team offsite for icebreaker sessions and other activities to ensure team members get to know each other.
  • D. Creating a project charter, documenting roles and responsibilities of each member, and sending it to the team members.

Answer: A

 

NEW QUESTION 39
During backlog refinement meeting, the new developer on the team asks the product owner to discuss a new performance threshold requirement and how it impacts the stories in the backlog. What should the team do?

  • A. Identify the tasks for the new performance threshold requirement
  • B. Add this threshold requirement request as acceptance criteria in all impacted stories
  • C. Create a spike story to analyze the impact of the threshold requirement on current stories
  • D. Conduct design planning session to review the performance threshold requirement

Answer: C

 

NEW QUESTION 40
The smallest amount of functionality that delivers customer value is best described as a:

  • A. Userstory map.
  • B. Minimum marketable feature.
  • C. Right sized story.
  • D. Function point analysis.

Answer: B

Explanation:
Explanation/Reference:

 

NEW QUESTION 41
What is a high-level representation of the features or themes that are to be delivered in each release?

  • A. Product Backlog
  • B. Product roadmap
  • C. Iteration plan
  • D. Release plan

Answer: B

Explanation:
Explanation/Reference:
Explanation:

 

NEW QUESTION 42
What is the responsibility of an extreme Programming (XP) customer role?

  • A. Testing the daily increments of the software developed
  • B. Interacting closely with users and representing the XP team
  • C. Planning and task allocation for the developer and tester
  • D. Writing the stories and acceptance tests for each story

Answer: D

 

NEW QUESTION 43
Which of the following is critical for the success of distributed Agile teams?

  • A. Shared knowledge
  • B. Cost containment
  • C. High volume of communication
  • D. Culture of collaboration

Answer: D

Explanation:
Explanation/Reference:
Explanation:

 

NEW QUESTION 44
The Agile artifact that describes the incremental nature of how a product will be built and delivered over time, along with the important factors that drive each individual release is called:

  • A. Product Theme
  • B. Product Wirframe
  • C. Product Vision Statement
  • D. Product Roadmap

Answer: D

 

NEW QUESTION 45
An agile project leader is delivering a team kick-off session. The first exercise is a "Life Timeline" ?a story- telling exercise where each team member tells their life story, explains how they experienced the highs and lows of their journey, and identifies their fears and hopes.
What is the project leader trying to create?

  • A. A safe space for team members to learn about each other's weaknesses and strengths.
  • B. A safe space for team members to learn to trust one another, leading to collaborative relationships.
  • C. A safe space for team members to learn to share, leading to collaborative relationships.
  • D. A safe space for team members to learn to be vulnerable, leading to high performance relationships.

Answer: C

 

NEW QUESTION 46
The three questions asked at every Daily Scrum should be: "What have you accomplished since the last Daily Scrum?";"What are you planning to accomplish between now and the next Daily Scrum?"; and:

  • A. What is yourcurrent performance velocity?
  • B. How many story pointswill you complete this sprint?
  • C. Are you on track to complete assigned story points?
  • D. What is preventing you from completing your work effectively?

Answer: D

Explanation:
Explanation
Explanation/Reference:

 

NEW QUESTION 47
......


The benefit in Obtaining the PMI-ACP Exam Certification

  • PMI-Agile Certified Practitioner will be confident and stand different from others as their skills are more trained than non-certified professionals.
  • PMI-Agile Certified Practitioner Certifications provide opportunities to get a job easily in which they are interested in instead of wasting years and ending without getting any experience.
  • PMI-Agile Certified Practitioner Certification provides practical experience to candidates from all the aspects to be a proficient worker in the organization.
  • PMI-Agile Certified Practitioner has more useful and relevant networks that help them in setting career goals for themselves. PMI-Agile Certified Practitioner Certification provides them with the right career direction than non certified usually are unable to get.
  • PMI-Agile Certified Practitioner is distinguished among competitors. PMI-Agile Certified Practitioner certification can give them an edge at that time easily when candidates appear for a job interview employers seek to notify something which differentiates the individual to another.

Difficulty in writing PMI-ACP Exam

This exam is very difficult especially for those who have not on the job experience as an PMI Certified Expert. Candidates can not pass this exam with only taking courses because courses do not provide the knowledge and skills that are necessary to pass this exam. ExamDumpsVCE is the best platform for those who want to pass PMI PMI-ACP with good grades in no time. ExamDumpsVCE provides the latest PMI PMI-ACP exam dumps that will immensely help candidates to get good grades in their final PMI PMI-ACP exam. ExamDumpsVCE is one of the best study sources to provide the most updated PMI PMI-ACP Dumps with our Actual PMI PMI-ACP Exam Questions PDF. Candidate can rest guaranteed that they will pass their PMI PMI-ACP Exam on the first attempt. We will also save candidates valuable time. ExamDumpsVCE Dumps help to pass the exam easily. Candidates can get all real questions from ExamDumpsVCE. One of the best parts is we also provide most updated PMI Certified Expert Exam study materials and we also want a candidate to be able to access study materials easily whenever they want. So, We provide all our PMI PMI-ACP exam questions in a very common PDF format that is accessible from all devices.

 

Get 2022 Updated Free PMI PMI-ACP Exam Questions and Answer: https://www.examdumpsvce.com/PMI-ACP-valid-exam-dumps.html

PMI-ACP Dumps PDF and Test Engine Exam Questions: https://drive.google.com/open?id=1t7rJh2ygkKhrfBRoeMoiKOwpTxRBNLtq