2024 Updated Verified LEED-Green-Associate Q&As - Pass Guarantee or Full Refund
[Apr-2024] LEED-Green-Associate Certification with Actual Questions from ExamDumpsVCE
NEW QUESTION # 81
EPA's ENERGY STAR Portfolio Manager is used for measuring
- A. only ongoing energy performance
- B. only ongoing water performance
- C. embodied energy
- D. ongoing energy and water performance
Answer: D
Explanation:
Explanation
EPA's ENERGY STAR Portfolio Manager is a no-cost, interactive energy management tool that allows you to securely track and assess energy and water consumption across your building portfolio12. You can use Portfolio Manager to benchmark your building's performance, set investment priorities, verify savings, and apply for ENERGY STAR certification23. Portfolio Manager does not measure embodied energy, which is the total amount of energy required to produce, transport, and install building materials.
NEW QUESTION # 82
Which third party certification is recommended to use when specifying sustainable cleaning products?
- A. Green Seal'™'
- B. Green Label Plus*
- C. Design for the Environment
- D. Greenguard"
Answer: A
Explanation:
Explanation
Green Seal is a third-party certification program that evaluates the environmental impacts of cleaning products and services. It has standards for various categories of products, such as cleaners, paper products, hand soaps, and floor care. Green Seal certified products meet rigorous performance, health, and environmental criteria.
By using Green Seal certified products, projects can reduce the exposure of building occupants and maintenance personnel to potentially harmful chemicals, improve indoor air quality, and support sustainable purchasing practices. References: LEED v4 Reference Guide for Building Operations and Maintenance, p. 109 1; Green Seal website
NEW QUESTION # 83
The result of proper design and operation of buildings and neighborhoods is an increase in energy
- A. supply
- B. demand
- C. efficiency
- D. consumption
Answer: C
Explanation:
The result of proper design and operation of buildings and neighborhoods is an increase in energy efficiency. Energy efficiency is the ratio of useful output to energy input for a system or process. Energy efficiency can be improved by using less energy to perform the same function or by using renewable or low-impact energy sources. Energy efficiency can reduce greenhouse gas emissions, energy costs, and dependence on fossil fuels1 . Reference: LEED v4 Green Associate Candidate Handbook1, EPA's Energy Efficiency
NEW QUESTION # 84
Which of the following Is a measure of energy use intensity?
- A. Systems with ENERGY STAR" requirements
- B. Energy consumed per unit of floor space
- C. The amount of electricity a wind turbine can produce
- D. Daylighting and views
Answer: B
Explanation:
Energy use intensity (EUI) is a measure of energy use per unit of floor space. It is calculated by dividing the total energy consumed by the building in one year (measured in kilowatt-hours or kilo-British Thermal Units) by the total gross floor area of the building (measured in square feet or square meters). EUI is a useful metric for comparing the energy performance of different buildings or benchmarking against national averages. EUI can vary depending on building type, climate, occupancy, and other factors. Generally, a lower EUI indicates better energy efficiency and lower environmental impact. Reference: What is Energy Use Intensity (EUI)?2; Energy Use Intensity (EUI)3
NEW QUESTION # 85
Which of the following facilitates the recharging of aquifers?
- A. Impervious paving
- B. Concrete parking lot
- C. Asphalt road
- D. Pervious paving
Answer: D
Explanation:
Explanation
Pervious paving, also known as permeable paving, allows water to pass through it, facilitating the recharging of aquifers. This type of paving reduces runoff by allowing water to soak into the ground, which can help replenish groundwater supplies and reduce the impact on nearby water bodies. References: LEED Green Associate Candidate Handbook, U.S. Green Building Council resources
NEW QUESTION # 86
Which Is a component of a construction waste management plan?
- A. Distance of the recycling facility from the project site
- B. Quantity of waste generated from excavated soil
- C. List of materials to be diverted from disposal
- D. Projected cost savings from diverting waste
Answer: C
Explanation:
A list of materials to be diverted from disposal is a component of a construction waste management plan. A construction waste management plan is a document that outlines the goals, procedures, and responsibilities for diverting construction and demolition waste from landfills or incinerators. A list of materials to be diverted from disposal identifies the types and quantities of materials that can be recycled, reused, salvaged, or donated, as well as the destinations and methods for diversion. The other options are not components of a construction waste management plan. Projected cost savings from diverting waste is a potential benefit of implementing a construction waste management plan, but it is not a required component. Quantity of waste generated from excavated soil is a factor that affects the construction waste generation rate, but it is not a component of a construction waste management plan. Distance of the recycling facility from the project site is a factor that affects the transportation emissions and costs associated with diverting waste, but it is not a component of a construction waste management plan. Reference: LEED Green Associate Candidate Handbook, page 28; USGBC, [Materials and Resources], page 3.
NEW QUESTION # 87
Which strategy is an example of permanent entryway systems used to reduce dust, dirt and contaminants brought into a facility?
- A. Providing sensors at all entrances
- B. Placing grilles, grates or mats at all major entrances
- C. Conducting a thermal comfort survey
- D. Installing outdoor air monitoring equipment
Answer: B
Explanation:
Permanent entryway systems are designed to capture dirt and particulates entering the building at regularly used exterior entrances. They can be grilles, grates, mats or other materials that are at least 10 feet long in the primary direction of travel12. They can improve indoor air quality, reduce maintenance costs and enhance floor appearance3.
Reference:
Entryway Systems | LEEDuser
lengths of the permanent entryway systems | LEEDuser
SC LEE Credit Contributions - CS Group
NEW QUESTION # 88
What are the values and benefits of building green?
- A. It will encourage others to build green
- B. It will enhance the health of the building occupants
- C. It is not as expensive to build as conventional design buildings
- D. It will lower the price for green materials
Answer: B
Explanation:
Explanation
One of the values and benefits of building green is that it will enhance the health of the building occupants.
Building green is a process that incorporates environmental considerations into every stage of a building's life cycle, from design to construction to operation to end-of-life. Building green can improve the indoor environmental quality (IEQ) of a building, which is thephysical and psychological conditions of the indoor spaces that affect the health, comfort, and productivity of the occupants. Building green can enhance IEQ by using low-emitting materials, providing adequate ventilation, controlling temperature and humidity, optimizing daylighting and lighting quality, reducing noise levels, and promoting occupant well-being12. References: LEED v4 Green Associate Candidate Handbook1, LEED v4 BD+C Reference Guide2
NEW QUESTION # 89
The LEED reviewer advised a project team that an inappropriate rating system was chosen for a newly constructed school in operation for one year and undergoing minor improvements. What should the project team have done differently to avoid this error?
- A. Review the appropriate rating system and determine the best adaptation to use with consultation from U.S. Green Building Council
- B. Allow the LEED Project Administrator sole responsibility to review the appropriate rating system for the project
- C. Select LEED for Existing Buildings: Operations and Maintenance Rating System, as the Operational and Maintenance phase has begun
- D. Select LEED for Schools New Construction and Major Renovations Rating System, as this project is classified as a school
Answer: A
NEW QUESTION # 90
An office without transit access can substantially reduce its transportation impact if
- A. the office is located at a major intersection
- B. workers are able to walk from the office to basic services
- C. green power is purchased to offset projected automobile travel
- D. ample parking spaces are provided
Answer: B
NEW QUESTION # 91
The Montreal Protocol banned the production of
- A. CFCs
- B. freon
- C. HCFCs
- D. ammonia
Answer: A
Explanation:
Explanation
The Montreal Protocol is an international treaty that aims to protect the ozone layer by phasing out the production and consumption of ozone-depleting substances (ODS). ODS are chemicals that contain chlorine or bromine, which can destroy the ozone molecules in the stratosphere. CFCs, or chlorofluorocarbons, are a group of ODS that were widely used in refrigeration, air conditioning, aerosols, and solvents. The Montreal Protocol banned the production of CFCs in 201012. Freon is a trade name for some CFCs and HCFCs, or hydrochlorofluorocarbons, which are also ODS but less harmful than CFCs. The Montreal Protocol also controls the production of HCFCs, which are being phased out gradually12. Ammonia is not an ODS and is not regulated by the Montreal Protocol1.
References:
The Montreal Protocol on Substances That Deplete the Ozone Layer | U.S. Department of State2 Montreal Protocol - Wikipedia1 The Montreal Protocol: fixing the ozone layer and taking climate action - Canada.ca3
NEW QUESTION # 92
Use of which of the following can help reduce the heat gain and peak air temperatures?
- A. Low albedo paving materials
- B. Pervious paving materials
- C. High reflectance roofing materials
- D. A drip irrigation system
Answer: C
Explanation:
High reflectance roofing materials can help reduce heat gain and peak air temperatures by reflecting more sunlight away from the building, thereby reducing the amount of heat absorbed by the roof. This can lead to lower cooling loads and energy use for air conditioning. Reference: LEED Green Associate Candidate Handbook, U.S. Green Building Council resources
NEW QUESTION # 93
In the commercial LEED Rating System, which point range will achieve the Certified level of certification?
- A. 40-49 points
- B. 30-39 points
- C. 50-59 points
- D. 60-69 points
Answer: A
Explanation:
Explanation
LEED certification is awarded based on the number of points a project earns across several categories of green building performance. The range of points required to achieve the Certified level of certification for the commercial LEED Rating System is 40-49, out of a possible 110 points. The other levels of LEED certification are: Silver (50-59 points), Gold (60-79 points), and Platinum (80 or more points)12. References:
LEED v4 Green Associate Candidate Handbook1, LEED v4 BD+C Reference Guide2
NEW QUESTION # 94
Which of the following contribute to the triple bottom line?
- A. Global security
- B. Project balance sheet
- C. Social responsibility
- D. Green metrics and verification
Answer: C
Explanation:
Explanation
Social responsibility is one of the factors that contribute to the triple bottom line. The triple bottom line is a framework that measures the performance of an organization or a project based on three dimensions:
environmental, social, and economic. Social responsibility refers to the ethical obligation of an organization or a project to consider the impacts of its decisions and actions on society and stakeholders, such as employees, customers, communities, and future generations. The other options are not factors that contribute to the triple bottom line. Global security is a broad concept that encompasses various aspects of international relations, suchas peace, human rights, justice, and cooperation. Project balance sheet is a financial statement that summarizes the assets, liabilities, and equity of a project at a given point in time. Green metrics and verification are tools and methods that quantify and validate the environmental performance of a project or a product. References: LEED Green Associate Candidate Handbook, page 31; USGBC [LEED v4 Impact Category: Triple Bottom Line], page 1.
NEW QUESTION # 95
A project plans to build a campus of buildings. Which of the following strategies should the project team consider to reduce energy demand?
- A. Design buildings to shade each other
- B. Enroll in a demand response program
- C. Select HVAC equipment without refrigerants
- D. Purchase carbon offsets
Answer: A
Explanation:
Designing buildings to shade each other can help reduce energy demand by decreasing cooling loads. By strategically positioning buildings on a site, it's possible to use the buildings themselves to block solar heat gain, reducing the need for air conditioning. Reference: LEED Green Associate Candidate Handbook, U.S. Green Building Council resources
NEW QUESTION # 96
A project team has three principal participants with LEED AP credentials. One is an energy modeler, one is a civil engineer and the third one is a general contractor. Under which category can their credentials contribute a point?
- A. Innovation
- B. Commissioning (Cx)
- C. Energy and Atmosphere
- D. Sustainable Sites
Answer: A
Explanation:
LEED AP credentials can contribute a point under the Innovation category, which rewards projects for achieving exceptional or innovative performance above the requirements set by the LEED rating system12. Having a LEED AP with specialty on the project team is one of the possible strategies to earn this point, as it demonstrates expertise and commitment to the green building process34. The specialty credential must match the rating system of the project4.
Reference:
Innovation | U.S. Green Building Council
LEED v4.1 BD+C | U.S. Green Building Council
Get a LEED AP with specialty on your team | LEEDuser
LEED professional credentials | U.S. Green Building Council
NEW QUESTION # 97
Who completes and signs the credit templates for a project pursuing LEED certification?
- A. The Commissioning (Cx) agent
- B. The certified LEED Reviewer
- C. The local authorities having jurisdiction
- D. The specified team member
Answer: D
Explanation:
The credit templates are the online forms that document the achievement of the LEED credits for a project pursuing LEED certification. The credit templates are completed and signed by the specified team member who is responsible for the credit, such as the architect, engineer, contractor, or owner. The team member must provide the required information, calculations, narratives, and supporting documentation for each credit13. Reference: LEED v4 Green Associate Candidate Handbook1, LEED v4 BD+C Reference Guide3
NEW QUESTION # 98
What standard ensures adequate ventilation is supplied to building occupants?
- A. ASHRAE 55
- B. ASHRAE 189.1
- C. ASHRAE 90.1
- D. ASHRAE 62.1
Answer: D
NEW QUESTION # 99
Which of the following is an appropriate usage of U.S. Green Building Council (USGBC) terminology for a LEED project?
- A. LEED Registered, Gold Building
- B. LEED Accredited Building
- C. LEED certified building
- D. LEED's certified building
Answer: C
Explanation:
The term "LEED certified building" is the correct usage according to the U.S. Green Building Council (USGBC). This term indicates that a building has met the standards set by the LEED rating system and has been officially certified by the USGBC. Reference: LEED Green Associate Candidate Handbook, U.S. Green Building Council resources
NEW QUESTION # 100
The use of native plant species, captured rainwater and evapotranspiration controllers are all strategies that contribute to
- A. process water reduction
- B. outdoor water use reduction
- C. reducing graywater demand
- D. stormwater runoff control
Answer: B
Explanation:
Explanation
The use of native plant species, captured rainwater, and evapotranspiration controllers are all strategies that can contribute to reducing outdoor water use. Native plants are adapted to local conditions and typically require less water than non-native species. Captured rainwater can be used for irrigation, reducing the need for potable water. Evapotranspiration controllers adjust irrigation schedules based on weather conditions and plant needs, preventing overwatering. References: LEED Green Associate Candidate Handbook, U.S. Green Building Council resources
NEW QUESTION # 101
Which of the following may be awarded to a Green Building professional who "distinguishes professional leadership, contribution to the standards of practice and body of knowledge and continual improvement in the field"?
- A. LEED Fellow
- B. LEED Green Associate
- C. LEED for Homes Green Rater
- D. LEED AP
Answer: B
NEW QUESTION # 102
Utilizing recycled materials achieves the green building objective of
- A. promoting the use of virgin materials and resources
- B. minimizing the need for landfills
- C. encouraging environmentally responsible forest management
- D. increasing demand for products extracted and manufactured within the region
Answer: B
NEW QUESTION # 103
......
LEED-Green-Associate Real Valid Brain Dumps With 275 Questions: https://www.examdumpsvce.com/LEED-Green-Associate-valid-exam-dumps.html
Updated LEED-Green-Associate Dumps PDF: https://drive.google.com/open?id=17678mNmXRiFrbcQnuAyqn9F7YXsXG3Wi